Court or Agency |
Ruling or Order |
Determination |
Date |
Division of Fisheries and Wildlife (DFW) |
Final Decision on administrative appeal of DFW’s no-take determination |
Issued final determination that transmission lines would not result in a prohibited "take" under MESA and that DFW did not have jurisdiction to consider and apply MESA to facilities located in federal waters in Nantucket Sound. |
July 2, 2008 |
Barnstable Superior Court |
Town of Barnstable v. Cape Wind Associates, LLC, BACV2007-00506-A |
Judge Kane issued ruling dismissing several counts of lawsuit for lack of subject matter jurisdiction. This action was brought by the Town of Barnstable and citizens groups challenging the issuance of Sec. Bowles’ Certificate issued under the Massachusetts Environmental Policy Act (MEPA). |
June 17, 2008 |
Energy Facilities Siting Board (EFSB) |
Approval of Project Update under G.L. c. 164, § 69J; Approval under G.L. c. 164, § 72; Extension Granted |
Found that project changes meet EFSB standards; the transmission lines will serve the public convenience and will be consistent with the public interest; and granted extension for commencement of construction for three years. |
May 2, 2008 |
Minerals Management Service (MMS) |
Draft Environmental Impact Statement (DEIS) |
Issuance of favorable DEIS finding environmental impacts from the Wind Park to be minimal. |
January 11, 2008 |
Division of Fisheries and Wildlife |
Determination under Massachusetts Endangered Species Act (MESA), G.L. c. 131A |
Issued determination that the jurisdictional transmission lines would not result in a prohibited “take” under MESA |
July 17, 2007 |
Massachusetts Environmental Policy Act |
Secretary of EOEEA issued Certificate on Cape Wind’s Final Environmental Impact Report (FEIR) |
Secretary approved FEIR as complying with MEPA. |
March 29, 2007 |
MA Supreme Judicial Court |
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 448 Mass. 45 (2006) |
Upholding Energy Facilities Siting Board (EFSB) decision approving transmission lines pursuant to G.L. c. 164, § 69J. |
December 18, 2006 |
Energy Facilities Siting Board |
Approval of Petition to Construct and Operate Pursuant to G.L. c. 164, § 69J |
Found that transmission lines will provide a reliable energy supply for the Commonwealth consistent with the minimization of environmental impacts and costs. |
May 11, 2005 |
First Circuit Court of Appeals |
Alliance to Protect Nantucket Sound v. Department of the Army, 398 F.3d 105 (2005) |
Upheld District Court decision that Army Corps of Engineers (ACOE) had jurisdiction to issue permit for data tower in Nantucket Sound. |
February 16, 2005 |
First Circuit Court of Appeals |
Ten Taxpayer Citizens Group v. CapeWind Assocs., LLC, 373 F.3d 183 (2004) |
Upheld District Court decision that state permitting requirements cannot apply to federal waters in Nantucket Sound where Wind Park will be located. |
June 28, 2004 |
Federal District Court (Mass.) |
Alliance to Protect Nantucket Sound v. Department of the Army, 288 F.Supp. 2d 64 (2003) |
ACOE had jurisdiction to issue permit for data tower in Nantucket Sound, followed proper procedures and did not have to consider environmental impacts. |
September 18, 2003 |
Federal District Court (Mass.) |
Ten Taxpayers v. Cape Wind Associates, LLC, 278 F.Supp. 2d 98 (2003) |
Commonwealth has no jurisdiction to require state permits for data tower located in federal waters of Nantucket Sound. |
August 19, 2003 |
Source: